Task End Date: Estimated Effort

Task End Date: Estimated Effort

We noticed a behaviour difference (v11004) with a Task End Date when assigning Estimated Effort upon Create and on Edit. 

When creating a task with estimated effort, the system will save the start and end time correctly:



on Save:




but when you Edit the same task and adjust the Effort the Scheduled End date adjust to fit the Estimated Effort within a work day (ex: 9am - 5pm):



If you then go and Edit the task again and adjust the Scheduled End Date, the Task saves correctly with the new hour set (ie: 13:00:00):



Is this the expected behaviour or a bug? 